Providing critical oxygen delivery system to Dragon’s Heart Hospital

Providing critical oxygen delivery system to Dragon’s Heart Hospital

Providing critical oxygen delivery system to Dragon’s Heart Hospital

Dragon Heart COVID ward under construction

Project: Dragon’s Heart Hospital Principality Stadium

Client: N G Bailey / Cardiff & Vale University Health Board

Timing: April 2020

Value: £1.6M

 

Without oxygen the Dragon’s Heart Hospital, conceived as a response to the coronavirus pandemic, could not function. Demonstrating outstanding commitment, the Medical Gases’ team designed, delivered and installed a system serving 1586 beds at the Dragon’s Heart Hospital in the Principality Stadium in just four weeks.

 

Background

In light of the evolving COVID-19 pandemic, and the rising number of confirmed cases testing positive for Covid-19, Cardiff and Vale University Health Board identified that additional bed space would be needed to accommodate patients in the area.

The Principality Stadium was identified as a suitable venue to accommodate the anticipated increase in demand, and Ysbyty Calon y Ddraig – the Dragon’s Heart Hospital was conceived.

It took Medical Gases just three weeks (9th – 30th April) to install the oxygen terminals essential to the scheme, leaving a week free for commissioning to successfully deliver the project by the 7th May deadline.

 

The Challenge

The main challenge in delivering oxygen to terminals for the planned 2000 headspaces at the Dragon’s Heart Hospital was time. The hospital needed to be operational within weeks rather than months. Typically, a project of this scales takes two to three years to deliver, Dragon’s Heart had to be delivered in four weeks, from Medical Gases receiving the order to the system being operational. Working within the guidance and restrictions imposed as a response to Covid-19 added an additional complication to a challenging timetable and this was compounded by the Managing Director (On site project managing) contracting Covid-19 in the second week of the contract, followed by the company’s Technical Director, a commissioning engineer, senior project engineer and several members of the workshop team.

 

The Solution

 

  • Planning

Medical Gases did a considerable amount of organising so that on Thursday 20th February, when the order was received, the team were able to divert resources, including labour, plant, equipment and materials, from other projects immediately.

 

  • Manpower – mobilised and prepared

Medical Gases’ forward planning meant that 40 members of the team were immediately on the project. To complete the project Medical Gases’ labour manager arranged over 50 operatives on site. A further five project managers, four supervisors, two directors, a labour manager, a logistics manager and a support team of people in the office, in the factory and making deliveries were involved.

The logistics involved in achieving this included ensuring those on site had to be put through the necessary induction sessions, provided with access passes and PPE, found accommodation etc. All this was achieved in just three weeks.

To ensure as few delays as possible in getting the people and resources required on site, everyone involved in the project was issued with a document to present to police etc. as required, identifying them as carrying out essential work.

 

  • Working together

The delivery of Dragon’s Heart Hospital highlighted the value of the excellent working relationships Medical Gases has worked hard to build and maintain during its Thirty Seven years in the business:

Predictably, securing the necessary supplies during the Covid-19 shutdown was challenging and Medical Gases’ relationships with suppliers were paramount. Medical equipment manufacturer Precision UK in Stockport, whilst working under extreme pressure supplying the majority of the coronavirus emergency hospitals, still managed to manufacture the necessary medical equipment and provide the pipework, without which Medical Gases would not have been able to complete the project.

In the same way that Medical Gases has invested in building relations with suppliers, it has worked hard at developing its relations and reputation with the companies it works for. Which is how main contractor, N G Bailey approached Medical Gases for Dragon’s Heart.

Appreciating the need to properly look after those working on site delivering the contract, N G Bailey organised the re-opening of hotels to accommodate workers, arranging a room only service to stay within the shutdown guidance. They also arranged a free of charge temporary kitchen and dining room open from 7am to 2am on site, providing food and drink for workers 19 hours per day.

Dragon Heart COVID ward under construction
Dragon Heart COVID ward under construction

Knowledge and commitment

Few, if any, other companies could have achieved what Medical Gases has at the Principality Stadium. Being able to mobilise such a knowledgeable, committed team in such a short time is only possible when you have the longevity and scale inspire the loyalty that Medical Gases does. The company has worked hard over the last Thirty Severn plus business, developing relationships and knowledge, which means it can respond quickly and effectively when a challenge such as this presents itself.

Both onsite and offsite, the Medical Gases team pulled together to ensure the success of the project.

 For those on site, working under extreme pressure in terms of timing meant working fast and working long hours whilst maintaining Medical Gases standard of workmanship. One worker covered 47 000 steps in his shift, like most running around the site to get the job done. 12- 14 hour shifts meant staying away from home for three to four weeks continually, living in a hotel room where, for the safety of the hotel staff, there was no cleaning or room services.

“The commitment of the staff was a key factor. Everyone worked seven days a week. Everyone went the extra mile, whether that meant jumping in the car to deliver a part to Wales or anything else. I am so proud of my team and grateful to them. What they have achieved is incredible.”

Andrew Barrett, Managing Director

 

Maintaining Purity

Medical Gases is justly proud of delivering the Dragon’s Heart Hospital on schedule but as important as meeting the timing is ensuring the quality of the delivery. The project had to be signed off by the NHS Trust’s pharmacist, without which the facility is not fit for use, so all quality standards had to meet the pharmacist’s requirements. The project was signed off with no issues and exactly on time.

 

Medical Gases delivered this significant project at a speed not previously thought possible, and with no compromise on quality. It is a testament to all those involved. The Dragon’s Heart Hospital contract ran concurrently with a project to provide oxygen to the Royal London Hospital. We are immensely proud of all our staff, who have worked so hard to deliver, and showed their commitment in such challenging circumstances, and are grateful to the suppliers who went above and beyond to support them. Thank you all.

Providing essential oxygen systems for emergency COVID-19 Intensive Care facilities

Providing essential oxygen systems for emergency  COVID-19 Intensive Care facilities

Providing essential oxygen systems for emergency
COVID-19 Intensive Care facilities

stadium aerial shot

We are immensely proud of our team who worked around the clock at the start of the COVID-19 shutdown to deliver essential oxygen systems for three emergency COVID-19 Intensive Care facilities in London and Cardiff. Our dedicated teams demonstrated their commitment in extremely challenging circumstances delivering new facilities at The Royal London, Epsom General and The Dragons Heart Hospital, Principality Stadium, Cardiff. They were ably supported by our suppliers who went above and beyond their normal service to help us to deliver the projects on schedule, on budget with no compromise on quality.

 

Timing was the obvious challenge –  projects that would ordinarily take months to design, plan and install, had to be delivered in a matter of weeks to provide emergency additional capacity for coronavirus patients and relieve the pressure on existing hospital facilities. To be able to achieve this, our resources had to be temporarily diverted from existing projects, and installation teams worked twelve to fourteen-hour shifts, whist complying with the additional requirements of COVID-19 safe working, to deliver the projects on time. Maintaining the quality and the standards required was as crucial as the timing, and the projects had to be signed off by the NHS Trust’s pharmacist as fit for use, with all quality standards meeting the pharmacist’s requirements. All projects were signed off on time with no issues.

 

Predictably, securing the necessary materials during the COVID-19 shutdown was also challenging, and we relied heavily on the relationships we have built over the years with our supply chain who, whilst also working under extreme pressure supplying the majority of the coronavirus emergency hospitals, still managed to manufacture and supply the necessary medical equipment and pipework, without which we would not have been able to complete the projects.

 

Few companies have the depth of experience, knowledge, expertise and trusted supply partners we have accumulated over 40 years of designing and installing gas delivery systems, all of which contributed to us to succeeding in delivering these projects, in time scales which prior to the outbreak of the COVID-19 pandemic would not have been considered for projects of this size, without compromise on quality.